Feilding Wastewater Treatment Plant UV Upgrade
Manawatū-Whanganui, New Zealand

Client
Plant Capacity
Technology
Source Water
Quality Issue
Validated UV Performance for a Critical Discharge Point
FILTEC delivered a major UV disinfection upgrade at the Feilding Wastewater Treatment Plant, replacing ageing equipment with a validated TrojanUV3000Plus system.
Designed for peak flows of 1,250 m³/hr, the new open-channel system provides reliable E. coli reduction before treated wastewater is directed to land application or, when required, river discharge. The upgrade combines treatment performance, operational redundancy, automated cleaning and intelligent power control within the existing wastewater facility.
Achieving 4-Log Protozoa Removal During High Turbidity Events
Manawatū District Council required a wastewater UV disinfection upgrade capable of meeting current discharge requirements while providing greater reliability, efficiency and serviceability. The replacement system needed to integrate with the existing gravity-fed channels and maintain treatment continuity during installation.
Key requirements included:
Validated E. coli reduction
Capacity for peak wastewater flows
Integration within existing UV channels
Continued operation during installation
Improved servicing and parts availability
Lower whole-of-life operating costs

TrojanUV3000Plus Open-Channel UV System
FILTEC supplied and installed a TrojanUV3000Plus system engineered for flows up to 1,250 m³/hr. Two UV banks contain 11 modules each, with four low-pressure amalgam lamps per module. This 132-lamp configuration provides treatment redundancy and delivers a validated UV dose of 30 mJ/cm² at the design conditions - giving Council a robust treatment barrier, not simply a like-for-like equipment replacement.



Efficient and Maintainable Wastewater Disinfection
The system automatically adjusts lamp output and the number of operating banks to match changing flow and water quality conditions. This avoids using more power than treatment demands require. Trojan ActiClean-WW technology combines chemical and mechanical sleeve cleaning to maintain UV intensity, limit fouling and reduce manual intervention, helping the system sustain reliable disinfection performance between scheduled services.
Ongoing UV Service and Maintenance
FILTEC commissioned the system and provided operator training to support safe, confident plant operation. Our involvement continues well beyond handover through local technical support, preventative maintenance, replacement lamps and critical spare parts. Backed by extensive Trojan UV expertise, FILTEC gives Manawatū District Council direct access to the people, knowledge and components required to keep this critical treatment barrier performing properly.

UV Treatment Built for Long-Term Performance
The Feilding Wastewater Treatment Plant now has a modern, validated UV disinfection system designed around real operating conditions.
The upgrade provides:
Validated E. coli treatment
Capacity for flows up to 1,250 m³/hr
Two-bank operational redundancy
Automated lamp and bank control
Reduced cleaning and maintenance demands
Ongoing local service support
By combining proven Trojan technology with FILTEC’s delivery and service capability, the upgrade strengthens treatment reliability while giving Council a more efficient and maintainable system for the years ahead.

Download Project Profile
For a concise, printable overview of the Feilding Wastewater Treatment Plant UV Upgrade, download the project profile below.